New Build Updates
October 2021 Status

1 October 2021
Due to delays in financing and regulatory approval (due to backlog), the focus of the build team has been to get the ground floor operational as soon as possible - pending regulatory approval (which is in process):
Ground floor is almost 100% complete internally.
Main Wudu/Wash facilities will be cordoned off and work will commence once ground floor is operational.
Exterior: 80%
All external work required to open ground floor to be completed in the next month or so
January 2021 Status

1 January 2021
Each of the four floors/exterior are in different levels of completion:
Ground Floor: Ladies & Children – 80%
Main prayer hall: decorated and carpeted complete
Kitchen: nearing completion
Girls' classrooms: completed
Girls' restrooms: completed
Taziat Room: nearing completion
First Floor: Men and Children - 60%
Exterior: 60%