New Build Updates

October 2021 Status

1 October 2021, 11:00:00

Due to delays in financing and regulatory approval (due to backlog), the focus of the build team has been to get the ground floor operational as soon as possible - pending regulatory approval (which is in process):

Ground floor is almost 100% complete internally.
Main Wudu/Wash facilities will be cordoned off and work will commence once ground floor is operational.

Exterior: 80%
All external work required to open ground floor to be completed in the next month or so

January 2021 Status

1 January 2021, 12:00:00

Each of the four floors/exterior are in different levels of completion:

Ground Floor: Ladies & Children – 80%

Main prayer hall: decorated and carpeted complete

Kitchen: nearing completion
Girls' classrooms: completed
Girls' restrooms: completed

Taziat Room: nearing completion

First Floor: Men and Children - 60%

Exterior: 60%